The conceptual oil and mining project, in a summarized form, describes the activities of drilling and testing of the exploratory well Vukovar GT-1. Upon acceptance by MinGOR, it serves as the basis for the preparation of (a) environmental protection plan, (b) oil and mining project.

A public procurement procedure has been conducted for the service of preparing the conceptual oil and mining project for drilling and testing of the exploratory well Vukovar GT-1, as well as the oil and mining project for drilling and testing of the exploratory well Vukovar GT-1. The bid of the bidder FIKA ECO d.o.o. was selected as the most favorable, and on February 27, 2024, a contract for the procurement of the specified service was concluded.

Project Overview:
• Total project value: €259,470.62, of which non-refundable amount of funds is: €217,330.02 (83.76%)
• Project leader: City of Vukovar, Croatia
• Project partner: EFLA Consulting Engineers, Iceland
• Project implementation period: April 13, 2022, to April 12, 2024

CONTACT INFORMATION:
City of Vukovar, Dr. Franjo Tuđman 1, 32000 Vukovar, Croatia, +385 (0) 32 456 501
www.vukovar.hr, Ova e-mail adresa je zaštićena od spambota. Potrebno je omogućiti JavaScript da je vidite.,

Ministry of Regional Development and EU Funds, Miramarska cesta 22, 10 000 Zagreb, Croatia
www.mrrfeu.hr, Ova e-mail adresa je zaštićena od spambota. Potrebno je omogućiti JavaScript da je vidite.

Together for green Europe | www.eeagrants.hr

The "Clean Energy for Vukovar" project is financed by Iceland, Liechtenstein, and Norway through the Financial Mechanism of the European Economic Area (EEA) 2014–2021, with national co-financing from the Republic of Croatia within the "Energy and Climate Change" program. The content of this announcement is the sole responsibility of the City of Vukovar and does not in any way reflect the views of the Manager of the "Energy and Climate Change" Program.

footer